The project will be implemented within three years. After completion of the project the Center will operate at its own cost.

Milestone plan

Events Status/time
Establishment of the Project implementation group (PIG) Completed
Kick-off meeting and consultations of representatives of the RF Ministry of Natural Resources and Environment, UNIDO and PIG in Vienna. Completed
Workshop with participation of representatives of countries of the Eastern Europe, Caucasus and Central Asia in Tbilisi Completed
Search of partners for co-financing and participation Received prior consent of Danfoss and Rossoyuzkholodprom association.
For final arrangement and further extension of the list of partners, an opening date of the Regional center needs to be agreed
Discussion of a certification system for use in the Regional center with Russian refrigeration associations and WorldSkills Completed
Preparation of tender documents for the Center Completed
Selection of a beneficiary in Armenia Completed.
Anania Shirakatsi international lyceum was selected.
Holding of tenders for establishment of the Center Completed.
The winning bidders are OOO Atmosfera Komforta-M for supply of equipment and materials for establishment of the training center, and OOO SP Sodruzhestvo for adaptation, development and printing manuals and development of a web-portal and online courses
Selection of a place and potential partners for the pilot project(s) Completed.
The beneficiary for the pilot project will be selected later
Preparation of tender documents for the pilot project In process
Establishment of the infrastructure of the Center, development of interactive online courses (in Russian and English) and web-portal (in Russian and English) Subproject “Supply of equipment and materials for the training center”: from 27.03.2018 to 31.09.2018.
Subproject “Adaptation, development and printing manuals and development of a web-portal and online courses”: from 25.04.2018 to 31.09.2018
Holding of the tender for the pilot project Autumn 2018
Training of trainers and pilot group The training will be organized in thee steps:
  • training of trainers in Moscow from 12.08.2018 to 14.08.2018;
  • training of trainers in Yerevan — by 16.09.2018;
  • training of a pilot group will be organized after commissioning of the web-portal and teaching aids from December 2018 to February 2019
Establishment of the pilot project From October 2018 to end of February 2019
Launch of the pilot project
Public awareness activities
February–March 2019.
Additional approval by the RF Ministry of Natural Resources and Environment, Ministry of Nature Protection of the Republic of Armenia and UNIDO
Operation of the Center From March 2019 to February 2020.
Since February 2020, the Center will operate at its expense
Preparation of project implementation reports to the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol The report to be submitted in the end of March 2019

Dear visitor! The site www.ozoneprogram.ru uses cookies and similar technologies to improve the site's performance, efficiency and usability using reliable and personalized information. By continuing to browse the site, you agree to the use of cookies in accordance with the cookie warning on www.ozoneprogram.ru. If you do not agree with the use of cookies, please set up your browser or refuse to browse the site.